Haptic Backhoe Thesis Plan
Last updated 03/15/04 |
Scheduled time: |
|
Behind Schedule: |
|
Ahead of schedule: |
|
|
Complete
|
Task / Event
|
Jan
|
Feb
|
Mar
|
Apr
|
May
|
5-9 |
12-16 |
19-23 |
26-30 |
2-6 |
9-13 |
16-20 |
23-27 |
1-5 |
8-12 |
15-19 |
22-26 |
29-2 |
5-9 |
12-16 |
19-23 |
26-30 |
3-7 |
10-14 |
|
outline TOC |
15% |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
finish valve
model in Simulink |
60% |
60% |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
□ |
finish overall
backhoe model in Simulink |
|
0% |
0% |
0% |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
study some
other thesis examples |
|
0% |
0% |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
copy Kin-Dyn
section into LaTeX |
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
write
compliance section |
|
|
|
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
□ |
write intro |
|
|
|
20% |
20% |
20% |
20% |
20% |
20% |
20% |
|
|
|
|
|
|
|
|
|
□ |
write
literature review |
|
|
|
|
0% |
0% |
5% |
5% |
5% |
85% |
|
|
|
|
|
|
|
|
|
□ |
review "thesis
so far" w/Dr. Book |
|
|
|
|
|
|
0% |
0% |
0% |
0% |
|
|
|
|
|
|
|
|
|
|
create
bibliography file for LaTeX |
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
write HIL
simulator section |
|
|
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
write valve modeling
section |
|
|
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
write
simulation results section |
|
|
|
|
0% |
75% |
75% |
75% |
75% |
75% |
|
|
|
|
|
|
|
|
|
|
write 1 dof
design section |
|
|
|
|
0% |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
write 4 dof
design section |
|
|
|
|
|
|
0% |
0% |
0% |
X |
|
|
|
|
|
|
|
|
|
□ |
write haptics
testing section |
|
|
|
|
|
|
|
|
0% |
10% |
|
|
|
|
|
|
|
|
|
□ |
announce thesis
defense presentation |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
□ |
present /
defend |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
□ |
make thesis
corrections |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
□ |
submit approved
thesis to ME dept |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Work Plan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|